Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.025 0.05 0.02 0.04 0.025 0.05 0.02 0.04 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every change of gradient All of these At every 30 m intervals At every change of direction At every change of gradient All of these At every 30 m intervals ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating All of these Circular buildings Hexagonal buildings Octagonal buildings All of these Circular buildings Hexagonal buildings Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1000 m3 500 m3 1500 m3 2000 m3 1000 m3 500 m3 1500 m3 2000 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 80 cm 60 cm 75 cm to 80 cm 70 cm 80 cm 60 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP