Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings Circular buildings All of these Octagonal buildings Hexagonal buildings Circular buildings All of these Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made for stone work in square metre in case of (A) and (B) of the above Wall facing Building work Columns, lintels, copings (A) and (B) of the above Wall facing Building work Columns, lintels, copings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The end sections are parallel planes The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The end sections are parallel planes The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 ANSWER DOWNLOAD EXAMIANS APP