Estimating and Costing Referring of given figure, pick up the correct statement from the following: The total length of centre line of four walls is 20 m All listed here Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m All listed here Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Bottom of P trap W.C. Top of P trap W.C. Side of water closet Main soil pipe Bottom of P trap W.C. Top of P trap W.C. Side of water closet Main soil pipe ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP