Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is None of these 20 cm 15 cm 10 cm None of these 20 cm 15 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 1.00 cum 3.00 cum 2.00 cum 4.00 cum 1.00 cum 3.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the excavation where measurements are made in square meters for payment. Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m Both (B) and (C) Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m Both (B) and (C) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken All of these 1.35 for 20 users 1.80 liters for 5 to 10 users 1.20 liters for 15 users All of these 1.35 for 20 users 1.80 liters for 5 to 10 users 1.20 liters for 15 users ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters All of these Wall panels Floors Root slabs All of these Wall panels Floors Root slabs ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Main soil pipe Top of P trap W.C. Bottom of P trap W.C. Side of water closet Main soil pipe Top of P trap W.C. Bottom of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP