Estimating and Costing Berms are provided in canals if these are Fully in excavation Partly in excavation and partly in embankment Fully in embankment All of these Fully in excavation Partly in excavation and partly in embankment Fully in embankment All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 14° 10° 12° 8° 14° 10° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 10 cm 20 cm None of these 15 cm 10 cm 20 cm None of these 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area Wall thickness W' Area Room area Courtyard area Wall thickness W' Area Room area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP