Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 5.0 sqm 10 sqm 7.5 sqm 2.5 sqm 5.0 sqm 10 sqm 7.5 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Fully in embankment Fully in excavation All of these Partly in excavation and partly in embankment Fully in embankment Fully in excavation All of these Partly in excavation and partly in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Connection to drains All of these Bed concreting Setting and laying Connection to drains All of these Bed concreting Setting and laying ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 1.5 m2 4.0 m2 2.0 m2 5.0 m2 1.5 m2 4.0 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP