Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters All of these Root slabs Wall panels Floors All of these Root slabs Wall panels Floors ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Bib-cocks All of these Stop-cocks Ball valves Bib-cocks All of these Stop-cocks Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Interception manhole Intercepting trap All listed here Master trap Interception manhole Intercepting trap All listed here Master trap ANSWER DOWNLOAD EXAMIANS APP