Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and None of these Breadth of the wall One fourth breadth of wall on each side Half breadth of wall on each side None of these Breadth of the wall One fourth breadth of wall on each side Half breadth of wall on each side ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Cost of fittings and their fixing is specified for the following sanitary fittings Lavatory basins Water closets Flushing pipes All listed here Lavatory basins Water closets Flushing pipes All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.04 sqm 0.02 sqm 0.03 sqm 0.01 sqm 0.04 sqm 0.02 sqm 0.03 sqm 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.75 1 0.25 0.5 0.75 1 0.25 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these ANSWER DOWNLOAD EXAMIANS APP