Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 2.0 m2 1.5 m2 5.0 m2 4.0 m2 2.0 m2 1.5 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of Reinforced brick work Brick work in arches One or more than one brick wall Half brick wall Reinforced brick work Brick work in arches One or more than one brick wall Half brick wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is All listed here Rolling shutters Collapsible gates Ventilators and glazing All listed here Rolling shutters Collapsible gates Ventilators and glazing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 3.00 cum 4.00 cum 1.00 cum 2.00 cum 3.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is None of these Length, breadth, height Breadth, length, height Height, length, breadth None of these Length, breadth, height Breadth, length, height Height, length, breadth ANSWER DOWNLOAD EXAMIANS APP