Estimating and Costing The detention period in a septic tank is assumed 30 minutes 40 minutes 20 minutes 25 minutes 30 minutes 40 minutes 20 minutes 25 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are All of these Fully in excavation Partly in excavation and partly in embankment Fully in embankment All of these Fully in excavation Partly in excavation and partly in embankment Fully in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.247 m³ 0.295 m³ 0.200 m³ 0.274 m³ 0.247 m³ 0.295 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.5 0.75 1 0.25 0.5 0.75 1 0.25 ANSWER DOWNLOAD EXAMIANS APP