Estimating and Costing

Estimating and Costing
The most reliable estimate is

Preliminary estimate
Detailed estimate
Cube rate estimate
Plinth area estimate

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

27,000 m³
26,000 m³
27,500 m³
26,500 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The brick work is not measured in cu m in case of

Half brick wall
Reinforced brick work
Brick work in arches
One or more than one brick wall

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The concrete work for the following part of the building of specified thickness is measured in square meters

Wall panels
Root slabs
Floors
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is made for stone work in square metre in case of

Wall facing
Columns, lintels, copings
Building work
(A) and (B) of the above

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

2000 m3
500 m3
1000 m3
1500 m3

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑