Estimating and Costing

Estimating and Costing
The most reliable estimate is

Preliminary estimate
Detailed estimate
Cube rate estimate
Plinth area estimate

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The height of the sink of wash basin above floor level is kept

70 cm
60 cm
80 cm
75 cm to 80 cm

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is

d × d × s
L.D √(1 + s²)
2 L.D √(1 + s²)
√[d² × (ds)²]

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is made in square metre in case of

Hollow concrete block wall
R.C.C. structure
Cement concrete in foundation
None of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
While estimating the qualities for the construction of a building, the correct metric unit is

Liter for capacity
Cubic metre for area
Square meters for volume
Meter for length

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The weight of an item is measured correct to nearest

0.25 kg
1.00 kg
0.50 kg
0.75 kg

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑