Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 2000 m3 1500 m3 1000 m3 500 m3 2000 m3 1500 m3 1000 m3 500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Fully in excavation Fully in embankment All of these Partly in excavation and partly in embankment Fully in excavation Fully in embankment All of these Partly in excavation and partly in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 3.00 cum 4.00 cum 1.00 cum 2.00 cum 3.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken All of these 1.35 for 20 users 1.80 liters for 5 to 10 users 1.20 liters for 15 users All of these 1.35 for 20 users 1.80 liters for 5 to 10 users 1.20 liters for 15 users ANSWER DOWNLOAD EXAMIANS APP