Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Earth work in excavation Rock cutting Excavation in trenches for foundation All of these Earth work in excavation Rock cutting Excavation in trenches for foundation All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Fully in embankment Fully in excavation Partly in excavation and partly in embankment All of these Fully in embankment Fully in excavation Partly in excavation and partly in embankment All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area Room area W' Area Wall thickness Courtyard area Room area W' Area Wall thickness ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building All of these The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall All of these The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is None of these Height, breadth, length Length, breadth, height Breadth, length, height None of these Height, breadth, length Length, breadth, height Breadth, length, height ANSWER DOWNLOAD EXAMIANS APP