Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system All of these At every 30 m intervals At every change of direction At every change of gradient All of these At every 30 m intervals At every change of direction At every change of gradient ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Wall panels All of these Root slabs Floors Wall panels All of these Root slabs Floors ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Cutting Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation ANSWER DOWNLOAD EXAMIANS APP