Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Excavation Cutting Surface excavation Surface dressing Excavation Cutting Surface excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of Form works R.C. Chhajja Concrete Jeffries P.C. (Damp proof course) Form works R.C. Chhajja Concrete Jeffries P.C. (Damp proof course) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Specifications of works All of these Proportion of mortar Specifications of materials Specifications of works All of these Proportion of mortar Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 25 minutes 40 minutes 30 minutes 20 minutes 25 minutes 40 minutes 30 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall ANSWER DOWNLOAD EXAMIANS APP