Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.247 m³ 0.295 m³ 0.200 m³ 0.274 m³ 0.247 m³ 0.295 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L + (2 × 0.42 d) L - (0.42 d) L + 0.42 d L - (2 × 0.4 d) L + (2 × 0.42 d) L - (0.42 d) L + 0.42 d L - (2 × 0.4 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum All of these Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum All of these Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 30 D 50 D 39 D 59 D 30 D 50 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Cube rate estimate Detailed estimate Preliminary estimate Plinth area estimate Cube rate estimate Detailed estimate Preliminary estimate Plinth area estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.75 kg 0.25 kg 1.00 kg 0.50 kg 0.75 kg 0.25 kg 1.00 kg 0.50 kg ANSWER DOWNLOAD EXAMIANS APP