Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 150 mm 200 mm 100 mm 175 mm 150 mm 200 mm 100 mm 175 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Room area Wall thickness Courtyard area W' Area Room area Wall thickness Courtyard area W' Area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.50 kg 0.75 kg 0.25 kg 1.00 kg 0.50 kg 0.75 kg 0.25 kg 1.00 kg ANSWER DOWNLOAD EXAMIANS APP