Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes All of these Bed concreting Setting and laying Connection to drains All of these Bed concreting Setting and laying Connection to drains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate W' Area Wall thickness Room area Courtyard area W' Area Wall thickness Room area Courtyard area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Top of P trap W.C. Main soil pipe Side of water closet Bottom of P trap W.C. Top of P trap W.C. Main soil pipe Side of water closet Bottom of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every change of gradient At every 30 m intervals All of these At every change of direction At every change of gradient At every 30 m intervals All of these ANSWER DOWNLOAD EXAMIANS APP