Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 39 D 59 D 50 D 30 D 39 D 59 D 50 D 30 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every 30 m intervals All of these At every change of gradient At every change of direction At every 30 m intervals All of these At every change of gradient ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Availability of materials All of these Transportation of materials Quantity of the materials Availability of materials All of these Transportation of materials Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Liter for capacity Cubic metre for area Meter for length Square meters for volume Liter for capacity Cubic metre for area Meter for length Square meters for volume ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes All of these Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting Connection to drains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ ANSWER DOWNLOAD EXAMIANS APP