Estimating and Costing The measurement is not made in square meters in case of Concrete Jeffries Form works R.C. Chhajja P.C. (Damp proof course) Concrete Jeffries Form works R.C. Chhajja P.C. (Damp proof course) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at Right angle to the centre line Intermediate points having abrupt change in gradient 30 meters apart All of these Right angle to the centre line Intermediate points having abrupt change in gradient 30 meters apart All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Cub. m None of these Sq. m Meters Cub. m None of these Sq. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.04 sqm 0.01 sqm 0.03 sqm 0.02 sqm 0.04 sqm 0.01 sqm 0.03 sqm 0.02 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP