Estimating and Costing The following item of earth work is not measured separately. All listed here Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,500 m³ 26,000 m³ 27,000 m³ 27,500 m³ 26,500 m³ 26,000 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Wall thickness W' Area Courtyard area Room area Wall thickness W' Area Courtyard area Room area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes are classified according to their sizes and quality All of these Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality All of these Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item ANSWER DOWNLOAD EXAMIANS APP