For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

0.98 m³
0.94 m³
1.00 m³
0.90 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

0.02
0.05
0.04
0.025

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Pick up the item whose weight is added to the weight of respective item, is

All listed here
Cleats
Brackets
Bolts

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

½ (Bd + Sd2)
B + d + Sd
B × d - Sd1/2
Bd + Sd2

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The slope of the outlet of 'P trap' below the horizontal is kept

10°
12°
8°
14°

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

27,000 m³
26,000 m³
26,500 m³
27,500 m³

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑