Construction Planning and Management Construction team means All listed here An architect An engineer An owner All listed here An architect An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 15 days 10 days 8 days 9 days 15 days 10 days ANSWER DOWNLOAD EXAMIANS APP