Construction Planning and Management Construction team means All listed here An architect An owner An engineer All listed here An architect An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Increase of project completion time Decrease of project completion time Change of critical path All of these Increase of project completion time Decrease of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP