Construction Planning and Management Construction team means An owner An architect An engineer All listed here An owner An architect An engineer All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement ANSWER DOWNLOAD EXAMIANS APP