Construction Planning and Management Construction team means An engineer All listed here An owner An architect An engineer All listed here An owner An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 25 35 20 15 25 35 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest May be longest May be shortest Is always longest Is always shortest May be longest May be shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Avoids delays which are very common in bar charts Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here ANSWER DOWNLOAD EXAMIANS APP