Construction Planning and Management

Construction Planning and Management
Construction team means

An architect
An engineer
All listed here
An owner

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

8 days
10 days
15 days
9 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

Free float
Event
Constraint
Dummy

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The normal time required for the completion of project in the above problem is

13 days
19 days
14 days
9 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Updating may result in

Decrease of project completion time
All of these
Change of critical path
Increase of project completion time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

Equal to X
Less than X
Any of the above
More than X

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑