Construction Planning and Management Construction team means An owner All listed here An architect An engineer An owner All listed here An architect An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved Preceding activities None of these Succeeding activities The particular activity involved Preceding activities None of these Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme All listed here Is based on time estimate Synthesising in concepts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Normal time Standard time Crash time Optimistic time Normal time Standard time Crash time ANSWER DOWNLOAD EXAMIANS APP