Construction Planning and Management Construction team means An engineer An owner An architect All listed here An engineer An owner An architect All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between None of these Total float and independent float Free float and independent float Total float and free float None of these Total float and independent float Free float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP