Construction Planning and Management Construction team means An architect All listed here An owner An engineer An architect All listed here An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has None of these Minimum float Zero float Maximum float None of these Minimum float Zero float Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 4 2 3 1 4 2 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 20 25 15 35 20 25 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Minimum Maximum Infinite Zero Minimum Maximum Infinite Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP