Construction Planning and Management Construction team means An engineer All listed here An owner An architect An engineer All listed here An owner An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 35 20 25 15 35 20 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Dump truck Bulldozer Clam shell Scraper Dump truck Bulldozer Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Finishing, shaping and trimming Finishing and shaping Shaping and trimming Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming Trimming and finishing ANSWER DOWNLOAD EXAMIANS APP