Construction Planning and Management
Free float is mainly used to

Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of preceding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities