Construction Planning and Management Construction team means An architect An engineer All listed here An owner An architect An engineer All listed here An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 15 days 9 days 8 days 10 days 15 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Event Constraint Dummy Free float Event Constraint Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 14 days 9 days 13 days 19 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time All of these Change of critical path Increase of project completion time Decrease of project completion time All of these Change of critical path Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X Less than X Any of the above More than X Equal to X Less than X Any of the above More than X ANSWER DOWNLOAD EXAMIANS APP