Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Standard time Crash time Normal time Optimistic time Standard time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Junior Engineer Assistant Engineer Engineer Executive Engineer Junior Engineer Assistant Engineer Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Availability of labour All listed here Site survey Availability of construction materials Availability of labour All listed here Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct ANSWER DOWNLOAD EXAMIANS APP