Construction Planning and Management Grader is used mainly for Trimming and finishing Shaping and trimming Finishing and shaping Finishing, shaping and trimming Trimming and finishing Shaping and trimming Finishing and shaping Finishing, shaping and trimming ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Negative Zero Same Positive Negative Zero Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 27 minutes 21 minutes 15 minutes 20.143 minutes 27 minutes 21 minutes 15 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 14 days 9 days 19 days 13 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP