Construction Planning and Management Site order book is used for recording Construction measurements Issue of store equipments Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments Names of the casual labour Instructions by the executive engineers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Event Constraint Free float Dummy Event Constraint Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 4350 kg 3425 kg 2975 kg 5515 kg 4350 kg 3425 kg 2975 kg 5515 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP