Construction Planning and Management
Site order book is used for recording

Construction measurements
Issue of store equipments
Names of the casual labour
Instructions by the executive engineers

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

A part of the money kept in reserve for providing additional structures and structural modifications
The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float of the activity must be zero but independent float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Independent float must be zero but free float need not be zero

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Normal durations for all the activities

ANSWER DOWNLOAD EXAMIANS APP