Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 10 days 8 days 9 days 15 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 1 2 3 4 1 2 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 80 and 90 75 and 83 90 and 80 85 and 75 80 and 90 75 and 83 90 and 80 85 and 75 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels Unity of command Delegation of authority All listed here Effective control at all levels Unity of command Delegation of authority All listed here ANSWER DOWNLOAD EXAMIANS APP