Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Interfering float Total float Free float Duration Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 8,75,000 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 8,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Slow time Crash time Standard time Normal time Slow time Crash time Standard time Normal time ANSWER DOWNLOAD EXAMIANS APP