Construction Planning and Management What estimate would you give for the variance in above problem ? 54 36 81 9 54 36 81 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPA (Critical Path Analysis) CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) All listed here CPA (Critical Path Analysis) CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects All listed here Minor projects Any project Major projects All listed here Minor projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 2 4 1 3 2 4 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey Availability of labour All listed here ANSWER DOWNLOAD EXAMIANS APP