Construction Planning and Management What estimate would you give for the variance in above problem ? 54 81 36 9 54 81 36 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 None of these 14 19 24 None of these 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Construction measurements Issue of store equipments Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments Names of the casual labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Minimum Zero Maximum Infinite Minimum Zero Maximum ANSWER DOWNLOAD EXAMIANS APP