Construction Planning and Management
Preliminary project report for a road project must contain

The several alternatives of the project that have been considered
The contract documents for inviting tenders
The detailed estimated cost based on detailed design
The soil survey, traffic survey, concept design and approximate cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All listed here
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

A part of the money kept in reserve for providing additional structures and structural modifications
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over

ANSWER DOWNLOAD EXAMIANS APP