Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP