Construction Planning and Management Mile Stone charts were invented in the year of 1940 1930 1920 1910 1940 1930 1920 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 14 days 19 days 9 days 13 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Node All listed here Event Connector Node All listed here Event Connector ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is false but R is true A is true but R is false Both A and R is true and R is the correct explanation of A Both A and R is true but R is not the correct explanation of A A is false but R is true A is true but R is false Both A and R is true and R is the correct explanation of A Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP