Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of estimate Preparation of tender Survey of the site Initiation of proposal Preparation of estimate Preparation of tender Survey of the site Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always longest May be longest Is always shortest May be shortest Is always longest May be longest Is always shortest May be shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components ANSWER DOWNLOAD EXAMIANS APP