Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Duration Constraint Float Event Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Bulldozer Clam shell Dump truck Scraper Bulldozer Clam shell Dump truck Scraper ANSWER DOWNLOAD EXAMIANS APP