Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The detailed estimated cost based on detailed design
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
The several alternatives of the project that have been considered

ANSWER DOWNLOAD EXAMIANS APP