Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above Less than X Equal to X More than X Any of the above Less than X Equal to X More than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 15.9% and 97.7% 97.7% and 84.1% 97.7 % and 15.9% 2.3% and 84.1% 15.9% and 97.7% 97.7% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Preparation of estimate Survey of the site Initiation of proposal Preparation of tender Preparation of estimate Survey of the site Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Maximum cost Minimum cost Minimum time Maximum time Maximum cost Minimum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP