Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above Less than X Equal to X More than X Any of the above Less than X Equal to X More than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 250 kg Reduce by 250 kg Reduce by 200 kg Increase by 200 kg Increase by 250 kg Reduce by 250 kg Reduce by 200 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP