Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Tamping Kneading Vibration Pressing Tamping Kneading Vibration Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 15 minutes 27 minutes 21 minutes 20.143 minutes 15 minutes 27 minutes 21 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 8,75,000 Rs. 10,50,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 8,75,000 Rs. 10,50,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP