Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 81 36 54 9 81 36 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 19 days 14 days 9 days 13 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming ANSWER DOWNLOAD EXAMIANS APP