Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An owner An engineer All listed here An architect An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Kneading Vibration Tamping Pressing Kneading Vibration Tamping Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Loose sand Earth Concrete Ice Loose sand Earth Concrete Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 19 24 None of these 14 19 24 ANSWER DOWNLOAD EXAMIANS APP