Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be shortest Is always longest May be longest Is always shortest May be shortest Is always longest May be longest Is always shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 80 and 90 85 and 75 75 and 83 90 and 80 80 and 90 85 and 75 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Asphalt Firm earth Concrete Loose sand Asphalt Firm earth Concrete Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP