Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Finishing and shaping Trimming and finishing Finishing, shaping and trimming Shaping and trimming Finishing and shaping Trimming and finishing Finishing, shaping and trimming Shaping and trimming ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Maximum time Minimum cost Minimum time Maximum cost Maximum time Minimum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line and staff organization Functional organization Line organization None of these Line and staff organization Functional organization Line organization None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch ANSWER DOWNLOAD EXAMIANS APP