Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An owner An architect An engineer All listed here An owner An architect An engineer All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 3.7 years 7.87 years 5 years 4.23 years 3.7 years 7.87 years 5 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening ANSWER DOWNLOAD EXAMIANS APP