Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Reduce by 200 kg Increase by 200 kg Increase by 250 kg Reduce by 250 kg Reduce by 200 kg Increase by 200 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 15.9% and 97.7% 97.7% and 84.1% 97.7 % and 15.9% 2.3% and 84.1% 15.9% and 97.7% 97.7% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP