Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 6 days 4 days 16 days 10 days 6 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved Succeeding activities None of these Preceding activities The particular activity involved Succeeding activities None of these Preceding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 34500 Rs. 31050 Rs. 50000 Rs. 37950 Rs. 34500 Rs. 31050 Rs. 50000 Rs. 37950 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of assets and liabilities Comparison of profit and loss Economics of cost and benefits of the project Change in output due to change in input Comparison of assets and liabilities Comparison of profit and loss Economics of cost and benefits of the project Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP