Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 10 days 6 days 16 days 4 days 10 days 6 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Clam shell Scraper Bulldozer Dump truck Clam shell Scraper Bulldozer Dump truck ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An engineer An owner All listed here An architect An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Light construction Heavy construction Industrial construction Private construction Light construction Heavy construction Industrial construction Private construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP