Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 6 days 16 days 10 days 4 days 6 days 16 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 3425 kg 5515 kg 4350 kg 2975 kg 3425 kg 5515 kg 4350 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved None of these Succeeding activities Preceding activities The particular activity involved None of these Succeeding activities Preceding activities ANSWER DOWNLOAD EXAMIANS APP