Construction Planning and Management
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than latest event time of preceding node
less than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP