Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 15 minutes 27 minutes 20.143 minutes 21 minutes 15 minutes 27 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path ANSWER DOWNLOAD EXAMIANS APP