Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 6 days 16 days 4 days 10 days 6 days 16 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Small projects Deterministic activities Large and complex projects Research and development projects Small projects Deterministic activities Large and complex projects Research and development projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP