Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Highest cost slope Least cost slope Longest duration Shortest duration Highest cost slope Least cost slope Longest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Tampers Smooth-wheeled rollers Vibratory rollers Sheep foot rollers Tampers Smooth-wheeled rollers Vibratory rollers Sheep foot rollers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Interfering float Duration Free float Total float Interfering float Duration Free float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP