Construction Planning and Management
Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is

1, 3, 4, 2, 5
1, 2, 3, 4, 5
1, 2, 4, 3, 5
1, 3, 2, 4, 5