Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1930 1920 1910 1940 1930 1920 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP