Construction Planning and Management

Construction Planning and Management
Which one of the following represents an activity?

All listed here
Curing of concrete
Excavation for foundation
Setting of question paper

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which of the following does not represent an activity?

Foundation is being dug
The office area is being cleaned
The invitations are being sent
Site located

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

Concrete
Firm earth
Asphalt
Loose sand

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For completion of a project, the critical path of the network represents

Maximum time
Maximum cost
Minimum cost
Minimum time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Economic saving of time results by crashing

Cheapest noncritical activity
Cheapest critical activity
Costliest critical activity
Costliest noncritical activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

Free float
Total float
Duration
Interfering float

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑