Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Variation in cost in materials element, labour element and petrol-oil-lubricant element
Increase in rates of only important materials
Variation in total cost of the project on an ad hoc basis
Rate of inflation

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its latest start time and earliest start time
its latest finish time and earliest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its earliest finish time and latest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities

ANSWER DOWNLOAD EXAMIANS APP