Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 24 19 None of these 14 24 19 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP