Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 2 kg/tonne 20 kg/tonne 9 kg/tonne 6 kg/tonne 2 kg/tonne 20 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Light construction Private construction Industrial construction Heavy construction Light construction Private construction Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Moist loam Wet sticky clay Good common earth Well blasted rock Moist loam Wet sticky clay Good common earth Well blasted rock ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Dump truck Bulldozer Clam shell Scraper Dump truck Bulldozer Clam shell Scraper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP