Construction Planning and Management

Construction Planning and Management
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

6 kg/tonne
9 kg/tonne
2 kg/tonne
20 kg/tonne

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Interfering float is the difference between

Total float and independent float
Total float and free float
Free float and independent float
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

Reduce by 250 kg
Reduce by 200 kg
Increase by 250 kg
Increase by 200 kg

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

Rs. 8,43,750
Rs. 10,50,000
Rs. 11,56,250
Rs. 8,75,000

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

1, 2 and 4 are correct
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

4 and 5/6
5 and 25/36
3.5 and 5/6
3.5 and 25/36

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑