Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Critical ratio scheduling Event flow scheduling technique Slotting technique for scheduling Short interval scheduling Critical ratio scheduling Event flow scheduling technique Slotting technique for scheduling Short interval scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 80 and 90 85 and 75 90 and 80 75 and 83 80 and 90 85 and 75 90 and 80 75 and 83 ANSWER DOWNLOAD EXAMIANS APP