Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Expected time Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of labour Site survey Availability of construction materials All listed here Availability of labour Site survey Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 4,75,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs ANSWER DOWNLOAD EXAMIANS APP