Construction Planning and Management Completion of an activity on CPM network diagram, is generally known All listed here Node Event Connector All listed here Node Event Connector ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Horizontal lines Dots Crosses Vertical lines Horizontal lines Dots Crosses Vertical lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 10 days 4 days 6 days 16 days 10 days 4 days 6 days ANSWER DOWNLOAD EXAMIANS APP