Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is incorrect
Both A and R is correct
A is correct but R is not correct
R is correct but A is not correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oil-lubricant element
Rate of inflation
Variation in total cost of the project on an ad hoc basis