Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time Resources None of these Project duration time Both resources and project duration time Resources None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Shovel Dragline None of these Hoe Shovel Dragline None of these Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 6 days 4 days 10 days 16 days 6 days 4 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Shaping and trimming Trimming and finishing Finishing, shaping and trimming Finishing and shaping Shaping and trimming Trimming and finishing Finishing, shaping and trimming Finishing and shaping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Selecting sites Concrete cured Fixing of door Plastering of walls Selecting sites Concrete cured Fixing of door Plastering of walls ANSWER DOWNLOAD EXAMIANS APP