Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Resources Both resources and project duration time Project duration time None of these Resources Both resources and project duration time Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Survey of the site Preparation of estimate Initiation of proposal Preparation of tender Survey of the site Preparation of estimate Initiation of proposal Preparation of tender ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 4 days 16 days 10 days 6 days 4 days 16 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time Most likely time Expected time ANSWER DOWNLOAD EXAMIANS APP